Nambour Sewage Treatment Plant Upgrade

Nambour_Sewerage_Treatment_Plant

Project summary

  

Unitywater is planning a major upgrade to the Nambour Sewage Treatment Plant.

 

This treatment plant serves the catchments of Nambour, Woombye, Palmwoods, Yandina and Eumundi and is located to the east of Nambour beside the Bruce Highway and Petrie Creek.

 

The existing plant, which was last upgraded in 1998, is operating beyond its design capacity and requires an upgrade to cater for anticipated population growth in these catchments.

 

Unitywater is currently investigating options to increase the capacity of the Nambour Sewerage Treatment Plant to approximately 10 million litres/day to meet anticipated growth in the region.

 

By increasing the standard of treatment provided it will reduce the quantity of nutrients discharged to the lower reaches of the Maroochy river and result in a healthier river for the community.

Fast facts

Location Bli Bli Road, Nambour

Benefits

The Augmentation of the Nambour Treatment Plant will:

  • cater for the increasing population in the area;
  • increase the standard of treatment provided;
  • reduce the impact on the environment and improve the quality of water discharged to the Maroochy River; and
  • reduce odour emissions from the plant.
Commencement date Preliminary design and Contract document development is underway. Detailed design is expected to commence in November 2012.
Completion Commissioning is expected to be complete by June 2014.
 Supplier

A construction partner is yet to be determined.

Funding $44.5 million.

 

Project Background

The Nambour Sewage Treatment Plant was last upgraded in 1998 with a minor upgrade to the control system in 2006.

This sewage treatment plant currently treats an Average Dry Weather Flow (ADWF) of 6.7 million litres/day. Effluent from the plant is transferred by pipeline to Maroochydore where it is combined with effluent from the Maroochydore STP, and discharged into the lower reaches of the Maroochy River estuary. 

Project Details

Unitywater is reviewing options for the upgrade of the treatment plant to determine the most cost effective, environmentally beneficial solution.

The project procurement strategy is design and construction with early contractor involvement.  Three shortlisted contractors (Abigroup, CH2M HILL/Downer Joint Venture, and Tenix) have been selected to advise project details before providing their tender submissions for the design and construction of Nambour STP upgrade. Selection of the preferred tender submission is anticipated in the latter part of 2012 and design of the upgraded facilities will commence after engagement of the main contractor.

More information

If you have any questions or would like more information, please contact us.

 

Nambour_Sewerage_Treatment_Plant_catchment_map

Map of the Nambour Sewerage Treatment Plant catchment area

Nambour_Sewerage_Treatment_Plant

Aerial view of the existing Nambour Sewerage Treatment Plant