• The Aura Sewer Project will include installing a new sewer pump station and 14kms of new sewer pipe to transfer sewage to our Kawana Sewage Treatment Plant.
  • This major project is part of Unitywater’s regional investment to cater to the demands of population growth in an economical and environmentally sustainable way.
  • Construction is due to start in early 2023 and be completed in late 2024, weather and construction conditions permitting.
  • We will work closely with the local community and keep them informed of this project and any potential disruption.  
Aura Sewerage Project map

Project timeline

Late 2021
Complete design
Late 2022
Contract award
Early 2023
Commence construction
Late 2024
Construction completion