• The Harmony Water Project will include installing a new water supply, comprising water pipes and a new water reservoir.
  • This major water supply project is part of Unitywater’s regional investment to cater to the demands of population growth in an economical and environmentally sustainable way.
  • We will continue to work closely with local residents and businesses to update them about the project and to seek their feedback along the way.
  • Stage one of the Harmony Water Project is due to be operational by 2024 and includes 2.5km of water pipe and a new water reservoir.

 

Location

Harmony Estate, Palmview

Supplier

Unitywater

Design phase completion

Late 2021

Forecasted construction commencement

Early 2023

Forecast in-service date

Late 2024

Investment

$21.9 million


Harmony Water Project map

Project timeline

Late 2021
Complete design
Late 2022
Contract award
Early 2023
Commence construction
Late 2024
Stage 1 Project completion