Noosa Wastewater Treatment Plant is located on Wallum Lane, Noosa Heads.
The renewal and maintenance work will include:
- Geotech and surveying activities
- Structural renewal to concrete slabs, pits, and foundations
- Installation of pipes and fittings for the new wet weather bypass
- A new switch room and associated civil works, including installation of a new UV system.
Stage one of the upgrade works have been completed. This included installation of a new wet weather bypass to manage excess water flows during storm events, pipework, electrical conduits and associated construction works. Stage two of works, due to start later in 2025 will include a UV filter upgrade and stage three will see the existing switchboard replaced. It is expected that all works will be completed in 2026.
All works will take place within the existing Noosa Wastewater Treatment Plant.
Location – Wallum Lane, Noosa Heads
Commencement – October 2024
Completion – Early 2026