Unitywater is delivering a $64 million investment in water infrastructure through the Pine Valley Water Supply Project. The project includes the construction of a new 15 megalitre (ML) water reservoir in Morayfield and more than 8 kilometres of water pipeline to support growing communities across the region.

The new infrastructure will provide a safe and reliable water supply for the growing communities of Caboolture West, Morayfield and Narangba, where more than 100,000 new residents are expected to live over the next 20 years.

This investment will help provide a reliable and resilient water supply for current and future communities, supporting planned growth while maintaining the high-quality water services that customers rely on every day. By delivering infrastructure ahead of demand, Unitywater is helping build a stronger and more sustainable future for the City of Moreton Bay.

 

Construction of the Pine Valley Water Supply Project is underway and expected to be complete by mid-2027.

Project includes:

  • construction of a new 15 megalitre water reservoir at Jacko Place, Morayfield.
  • installation of more than 8 kilometres of water pipeline.
  • connections between the new reservoir and the existing water network.
  • construction and restoration work across multiple locations within the project area. 

 

Site offices and laydown areas have been established off Jacko Place and Forest Hills Drive, Morayfield.

Construction activities may impact residents and road users in the following areas:

  • Nairn Road
  • Jacko Place Road
  • Forest Hills Drive
  • Williamson Road
  • Oakey Flat Road
  • Elm Court
  • Ward Drive

Affected residents and businesses will be provided advance notice prior to works commencing.

View Pine Valley Water Supply Project map

Pine Valley supply map

 

Work crews are currently:

  • constructing the new water reservoir at Jacko Place
  • finalising road crossing works on Forest Hills Drive in preparation for pipe installation
  • completing the remaining air and scour valve installations.

Upcoming works late 2026:

  • permanent road restoration for Williamson Road, Forest Hills Drive and Oakey Flat Road.

Residents may notice:

  • construction vehicles and machinery entering and leaving the work area
  • increased noise from excavation and construction activities
  • temporary traffic changes, including reduced speed limits and lane closures
  • construction lighting if approved night works are required.

 

Why is Unitywater building a new water reservoir and pipelines?
The new water infrastructure will support population growth in the City of Moreton Bay. Over the next two decades, Caboolture West (Waraba), Morayfield South and Pine Valley will be the focus of urban development to accommodate more than 100,000 new residents. Unitywater will continue to upgrade and invest in water infrastructure in a sustainable way to meet the demands of our growing region.

What does the project include?
The Pine Valley Water Supply Project will deliver a new 15 megalitre (ML) reservoir and more than eight kilometres of water pipelines. The new water reservoir will be constructed within Unitywater-owned land at Jacko Place, Morayfield.

What communities will the new reservoir be serving?
The Pine Valley Water Supply Project will service the growing communities of Upper Caboolture, Morayfield and Narangba in the City of Moreton Bay local government area.

What stage is the project at?
The project is in the construction phase. Construction commenced in January 2025 and is expected to be completed by mid-2027, weather and site conditions permitting.

How long will it take to build?
Construction commenced in January 2025 and is expected to be completed by mid-2027, weather and site conditions permitting.

How will Unitywater minimise impact on residents and the local community?
The chosen location for the water pipelines is along existing road verges and within existing easements on private properties. This pipeline alignment was found to have the least impact on the environment and surrounding residents.

How will the project impact the environment?
Unitywater understands local vegetation and resident fauna and flora are highly valued by the community.

To allow for this essential project, there will be tree removal required at the Jacko Place reservoir site and at certain locations along the water pipeline alignment.

Unitywater has undertaken an extensive process of design and approvals to ensure, where possible, any potential impacts to the surrounding environment are minimised. 

Any trees marked for removal in the construction access area will be removed in accordance with City of Moreton Bay and Queensland Government requirements.

The Unitywater-owned land at Jacko Place has been cleared in parts by previous owners. Unitywater is committed as part of this project to revegetate the site with suitable flora to complement the existing ecosystem in Pine Valley. A minimum ratio of 1:6 (number of trees removed: number of trees replaced) revegetation will occur.

What environmental controls will be in place during the construction?
At Unitywater, we adhere to our Environmental Management Policy and operate under strict licenses from the Department of Environment and Science, Queensland.  

Our Environmental Management Strategy also outlines key measures that we undertake to look after local natural environments. These measures aim to help conserve the local environment and reduce the likelihood of potential environmental impacts resulting from the project.

The Pine Valley Water Supply Project will employ appropriate erosion and sediment controls during construction to prevent sediment impacting nearby watercourse and stormwater inlets and protect adjoining habitats and water quality.

Standard weed and pest hygiene and management practices will be implemented, consistent with the requirements of the Queensland Biosecurity Act 2014.

Standard hydrocarbon, waste, spill, acid sulphate soil and pollution management practices will be implemented.

Where possible we will investigate opportunities to recycle waste.

How will Cultural Heritage be protected as part of this project?
Unitywater acknowledges the Kabi Kabi People as the primary guardians, keepers, and knowledge holders of the land on which the project will be constructed.

Unitywater is working with the local First Nations Kabi Kabi people to ensure all Aboriginal Cultural Heritage will be protected, conserved, monitored and managed during project delivery.

How will the new water pipeline be installed?
Most sections of pipeline will be installed using open trenching methods, a common approach for constructing underground water infrastructure. This method allows the pipeline to be installed safely and connected to the existing water network.

What are the construction impacts of this project?
Residents along the water pipeline can reasonably expect trenching works construction impacts to include changed local traffic conditions, noise, dust and vibration. Throughout construction, Unitywater will ensure directly-impacted residents are kept well informed of the status of the works and the anticipated impacts.

How can I contact the project team?
Please contact the project's dedicated community and stakeholder engagement representative:

Ra Davies
Infrastructure Engagement Contact
0437 614 484
unitywater.projects@downergroup.com

 

Downer project team
Ra Davies
Infrastructure Engagement Contact
0437 614 484
unitywater.projects@downergroup.com

Other enquiries
Unitywater Contact Centre
1300 086 489
customer.service@unitywater.com

Project reference number
IF010231

Timeline

Mid 2024
Design complete
Late 2024
Investigations complete
Early 2025
Construction commenced
Mid 2027
Completion

News

Construction is underway on the new 15-megalitre reservoir at Jacko Place in Morayfield.

The reservoir’s base slab was poured using 270 cubic metres of concrete. The reservoir walls will be formed from 44 concrete panels, which will be raised vertically and secured in place.

The pour began at 2 am to take advantage of cooler temperatures, helping manage the concrete curing process and achieve a strong, durable foundation.

Watch the video to see the team carry out this major construction milestone.

Pine Valley - First stage of pipes installed with restoration works underwayPipe installation within private properties between Forest Hills Drive to Nairn Road, which is the first stage of our pipeline installation, is nearly complete. Our landscapers are now busy laying turf to restore any disturbed areas.

To ensure the successful establishment of the new turf, a 12-week maintenance plan is in place. This will include regular watering and ongoing monitoring to support healthy growth. Rather than use water trucks, an irrigation system will be installed to provide consistent and efficient watering. This will also minimise vehicle movement within the easement and protect the integrity of the site.

We thank the community for their continued patience and support.

Residents and people travelling through the area will have noticed that construction works have now officially started along Williamson Road. This is in addition to trenching works already underway along the existing Energex easement and at the new reservoir site off Jacko Place.

Our team has been door knocking and talking with directly impacted residents along Williamson Road about the works and the multiple laydown areas that will be set up to support our crews. The laydown areas will be set up intermittently as we progress down the road, helping to streamline activity.

Recyclable banner mesh, which has also been placed around the perimeter of the first lot of laydown areas, is keeping the area safely secured, looking neat and tidy, and clearly marked for everyone’s awareness.

Pine Valley - Crew rescues joey caught in a neighbour's fenceWhile hard at work, a couple of members of our trenching crew noticed a joey with its leg caught in a neighbouring fence. One of the crew gently helped to release the joey and, when it didn't hop away, quickly realised it may be injured or in shock and immediately contacted a local wildlife rescue group. Our crew member stayed with the joey until the rescue worker arrived.

The rescue worker sedated the injured joey so she could comfortably transport it back to her headquarters for injury management and treatment.

Pine Valley - Friendly reptile visitors on siteA Bearded Dragon and Nobbi Dragon were spotted by the project team while completing trenching works and were quickly moved to safety.

Our crews always keep an eye out for any wildlife that may be in the pathway of our works so that we can keep them safe and out of harms way. Spotting these two curious creatures was another reason for our project's Vegetation and Fauna Management Plan to be put into practice.

After the brief and friendly visit from our unexpected guests, we were able to release the reptiles back into the environment. Their care and release was overseen by a dedicated fauna specialist.

We've recently installed close to 100 nest boxes at the project's reservoir site to retain habitat for native owls, cockatoos, brush-tail and ringtail possums, microbats and small gliders.

There are seven different types of nest boxes. Each type varies in size with different-sized openings to cater for a variety of species at the site. A qualified tree climber selected the safest and most appropriate trees for each nest box.

We have established an ongoing maintenance plan and will continue to monitor the boxes; we are excited to see all the different species that find their way into the boxes to call them home.

Watch the video to find out more.

Pine Valley - New pipeline installation beginsWe've officially broken ground on the new pipeline installation. Works have started where the existing Energex easement crosses Forest Hills Drive. This marks a critical step forward to ensuring a reliable water supply for the community into the future.

Pine Valley - Site offices and the project laydown area are now operationalFollowing our previous update on the commencement of works for the Pine Valley Water Supply Project in Morayfield, we’re thrilled to share that our site offices and laydown area are officially up and running in Jacko Place, Morayfield. Security cameras and fencing are in place.

Pine Valley - Meeting with community

Our dedicated community engagement manager, Aleisha, has spent the best part of the last two weeks door knocking residents in the area who will be most impacted by works that will be happening within the Energex easement. She has been taking the time to understand their unique property needs, including access requirements and the safety of their pets, and has been explaining what they can expect during construction.

Aleisha will be their point of contact for the project, so it's been great that she's been able to meet with so many of the residents in person.

Aleisha is always two steps ahead of the construction schedule making sure that residents are advised well in advance of work beginning in the vicinity of their homes.